CA Intermediate · Advanced Accounting · AS 7 Construction Contracts
Navjyot Constructions is building a bridge for a state government. Its accountant is listing items for the contract cost under AS 7. Which of the following items should NOT be included in contract costs?
General administration costs without specified reimbursement in the contract are excluded from contract costs. Site insurance, directly related design and technical assistance, and depreciation of equipment used on the contract are all contract costs under AS 7, because they relate directly to the contract or can be allocated to it.
- AGeneral administration costs for which reimbursement is not specified in the contractCorrect
- BInsurance premium paid on the site and equipment used for the bridge contract
- CCosts of design and technical assistance directly related to the bridge
- DDepreciation of a crane used only on the bridge site
Explanation
Under AS 7, contract costs include costs that relate directly to the contract and costs attributable to contract activity in general that can be allocated to it, such as insurance, design and depreciation of equipment. General administration costs, selling costs and R&D costs are excluded unless the contract specifically reimburses them. Hence only the first item is excluded.
Did you get it right without looking?
One question tells you little. A timed set on AS 7 Construction Contracts shows your real accuracy, how long you take and where you lose marks.
More AS 7 Construction Contracts questions
- Ganga Infra Ltd is building a flyover for a state road authority under a fixed price contract and is compiling the contract costs under AS 7…
- Ganga Engineering Ltd. is building a bridge under a fixed price contract of Rs 300 lakh. At the reporting date, cost incurred is Rs 90 lakh …
- Vishwa Builders Ltd. has a fixed price contract for Rs 200 lakh. Up to the end of Year 1, costs incurred were Rs 60 lakh, of which Rs 10 lak…
- In 2025-26, Vindhya Engineers Ltd incurred ₹3 lakh on tendering for a bridge contract and charged it to the statement of profit and loss bec…
- Konark Infra Ltd. is building a flyover for a state government under a fixed price contract of Rs 80 lakh. At the year-end, costs incurred t…
- Narmada Constructions Ltd. has a fixed price contract of Rs 200 lakh. Year 1: costs incurred Rs 60 lakh, estimated further costs Rs 90 lakh.…