ACCA Applied Knowledge · Management Accounting · Budgetary control and reporting
Brandt Ltd's Assembly department budgeted 10,000 units at a variable cost of $12 per unit and fixed costs of $50,000, of which $20,000 is an apportioned share of head office costs not controllable by the department manager. Actual output was 11,000 units with total actual costs of $196,000, including $22,000 head office apportionment. What is the controllable cost variance for the manager, using a flexed budget?
The controllable cost variance is $12,000 adverse: actual controllable costs of $174,000 against a flexed controllable budget of $162,000.
- A$4,000 adverse
- B$12,000 adverseCorrect
- C$8,000 favourable
- D$2,000 adverse
Explanation
Flexed controllable budget = 11,000 x $12 + ($50,000 - $20,000) = $132,000 + $30,000 = $162,000. Actual controllable cost = $196,000 - $22,000 = $174,000. Controllable variance = $174,000 - $162,000 = $12,000, which is adverse because actual cost exceeds the flexed budget. The head office apportionment is excluded because the manager cannot control it.
Did you get it right without looking?
One question tells you little. A timed set on Budgetary control and reporting shows your real accuracy, how long you take and where you lose marks.
More Budgetary control and reporting questions
- A department's original budget was 2,000 labour hours at $15 per hour. Actual output required 2,300 hours in the flexed budget, and actual l…
- A company's monthly budgetary control report compares actual results with the original fixed budget. Actual output was 12,000 units against …
- Budgeted production at Orion Ltd was 10,000 units, with fixed overheads of $80,000 and variable overheads of $3 per unit. Actual production …
- A company's budget for a period was 5,000 units of output at a total cost of $60,000, of which $20,000 is fixed. Actual output was 5,500 uni…
- A company's budget for a period was 8,000 units at a total cost of $96,000, of which $40,000 is fixed. Actual output was 9,000 units and act…
- A department's budget for the year was $240,000 and managers know that unspent budget is cut next year. In the last month, the manager buys …