ACCA Applied Skills · Corporate and Business Law (Global) · Obligations of the seller and buyer, and provisions common to both
Corvin Co contracted under the CISG to buy 1,000 tonnes of grain from Dalmar Ltd, delivery by 1 March. Dalmar has not delivered by that date. Corvin does not want to avoid the contract yet but wants to give Dalmar more time. What may Corvin do?
Corvin may fix an additional reasonable period for delivery. If Dalmar still fails to deliver within that period, or says it will not, Corvin may then avoid the contract. Late delivery alone is not automatically a fundamental breach, and the CISG has no automatic termination rule.
- AFix an additional period of reasonable length for performance, and avoid if Dalmar does not deliver within itCorrect
- BAvoid the contract immediately because any late delivery is a fundamental breach
- CTreat the contract as automatically terminated after seven days of delay
Explanation
The CISG allows the buyer to fix an additional period of reasonable length (Nachfrist). If the seller fails to deliver within that period, or declares it will not, the buyer may avoid. Late delivery alone is not automatically fundamental, and there is no automatic termination after seven days.
Did you get it right without looking?
One question tells you little. A timed set on Obligations of the seller and buyer, and provisions common to both shows your real accuracy, how long you take and where you lose marks.
More Obligations of the seller and buyer, and provisions common to both questions
- Fenmark Ltd agreed to sell 200 crates of components to Gale Corp for delivery by carrier. Fenmark handed the goods to the carrier but did no…
- Jarvis Foods sold a consignment of fresh fruit to Kestrel Ltd under the CISG. Kestrel rightly rejects the fruit, which is subject to rapid d…
- Under a CISG contract, Gamma SA delivers goods that do not conform to the contract. Delta Co, the buyer, examined them promptly but then wai…
- Ostrava plc agrees to buy 2,000 units from Lindqvist AB under the CISG. The contract fixes a price but gives no payment date, and no other r…
- Vantor Ltd, a seller, failed to deliver on time because its own supplier, a third party hired to produce a component, defaulted. The supplie…
- Gantry Ltd sold goods to Holm SA under the CISG. Holm's market for the goods then collapsed and Holm refused to accept delivery, wrongly. Ga…