A company reports an adverse labour efficiency variance together with a favourable labour rate variance. Which explanation is most consistent with both?

Using cheaper, less skilled workers is the consistent explanation. They are paid below the standard rate, giving a favourable rate variance, but they work more slowly, so more hours are needed per unit and the efficiency variance is adverse.

  1. ACheaper, less skilled workers were usedCorrect
  2. BMore highly skilled, higher-paid workers were used
  3. COvertime premiums were paid more than planned
  4. DA machine breakdown caused workers to wait

Explanation

Lower-skilled staff are paid less than the standard rate (favourable rate) but take longer per unit (adverse efficiency). Skilled higher-paid staff would give the opposite pattern. Overtime would be adverse rate, and machine breakdown creates idle time rather than a favourable rate.