Dunmore Ltd budgeted 10,000 units and 20,000 labour hours, with fixed overheads of $80,000. Actual output was 10,500 units, taking 20,800 hours, and actual fixed overhead was $82,000. What is the fixed overhead volume efficiency variance?
The volume efficiency variance is $800 favourable. Actual output of 10,500 units should take 21,000 hours at 2 hours per unit, but only 20,800 were used. The 200 hours saved are valued at the $4 per hour fixed overhead rate.
- A$2,400 favourableCorrect
- B$2,400 adverse
- C$800 favourable
- D$3,200 favourable
Explanation
Rate = $80,000/20,000 hours = $4 per hour. Standard hours for actual output = 10,500 x 2 = 21,000. Efficiency variance = (21,000 - 20,800) x $4 = $800 favourable. Hence the correct figure is $800 favourable, not $2,400.
Did you get it right without looking?
One question tells you little. A timed set on Variance calculations and analysis shows your real accuracy, how long you take and where you lose marks.
More Variance calculations and analysis questions
- Budgeted profit for a period was $80,000. The variances were: total favourable $12,000 and total adverse $18,500. Assuming there are no othe…
- Standard labour is 3 hours per unit at $12.00 per hour. Dorset Co produced 1,200 units, using 3,750 hours at an actual rate of $12.40 per ho…
- A company's fixed overhead expenditure variance is $2,000 adverse and its volume variance is $5,000 favourable. What is the total fixed over…
- Which statement about a possible cause of a favourable material price variance combined with an adverse material usage variance is most like…
- Dunmore Co values material purchases at standard price on receipt and calculates the price variance at the time of purchase. It bought 10,00…
- Which statement about fixed overhead variances in a standard marginal costing system is correct?