Dunmore Ltd has a standard labour rate of $15 per hour. In May, 2,000 hours were paid for at an actual cost of $31,000, and 100 hours were idle. What is the labour rate variance for May, calculated on all hours paid?
The labour rate variance is $1,000 adverse. All 2,000 hours paid should have cost $30,000 at the standard $15 rate, but the actual cost was $31,000, so the extra $1,000 is an adverse rate variance, unaffected by idle time.
- A$1,000 adverseCorrect
- B$1,500 adverse
- C$1,000 favourable
- D$500 adverse
Explanation
Rate variance uses hours paid: 2,000 x $15 = $30,000 standard cost, against actual $31,000, giving $1,000 adverse. Idle time does not change the rate variance because it is calculated on all hours paid. Using only the 1,900 worked hours would give a wrong answer.
Did you get it right without looking?
One question tells you little. A timed set on Variance calculations and analysis shows your real accuracy, how long you take and where you lose marks.
More Variance calculations and analysis questions
- The standard price of material is $4.00 per kg. During the month, Ridley Ltd purchased 5,000 kg at a total cost of $21,500 and used 4,200 kg…
- Orla Co budgeted to sell 10,000 units at $20 each with a standard variable cost of $12 per unit. Actual sales were 9,500 units, with revenue…
- Harlow Ltd pays its production workers $12 per hour. In April, 5,000 hours were paid for, of which 400 hours were idle because of a machine …
- A company sets its standards on the assumption of perfect operating conditions, with no machine breakdowns, no idle time and no material was…
- Torrin Co uses absorption costing and a standard fixed overhead absorption rate of $8 per labour hour. Budgeted output was 5,000 units at 2 …
- Marlow Co uses absorption costing. Budgeted fixed overheads were $90,000 for 15,000 units, giving an absorption rate of $6 per unit. Actual …