Harlow Ltd uses absorption costing. Budgeted fixed overheads were $40,000 for 2,000 units, with each unit taking 2 labour hours. Actual output was 2,100 units, actual labour hours were 4,300 and actual fixed overhead was $42,500. What is the fixed overhead volume variance?
The fixed overhead volume variance is $2,000 favourable. The absorption rate is $20 per unit, and output was 100 units above the budget of 2,000. Over-production leads to over-absorption, so the variance is favourable. The $2,500 adverse figure is the expenditure variance instead.
- A$2,000 favourableCorrect
- B$2,000 adverse
- C$2,500 adverse
- D$500 adverse
Explanation
The absorption rate per unit is $40,000 / 2,000 = $20. Actual output exceeded budget by 100 units, so the volume variance is 100 x $20 = $2,000 favourable. $2,500 adverse is the expenditure variance ($40,000 - $42,500). $500 adverse is the total fixed overhead variance, being absorbed $42,000 less actual $42,500.
Did you get it right without looking?
One question tells you little. A timed set on Variance calculations and analysis shows your real accuracy, how long you take and where you lose marks.
More Variance calculations and analysis questions
- Zeta Ltd uses standard marginal costing. Budgeted sales were 2,000 units and actual sales were 2,150 units. The standard contribution is $12…
- Brindle Co has a standard labour rate of $9 per hour. In June, 3,200 hours were paid at an actual cost of $30,080, of which 150 hours were r…
- Kestrel Ltd budgeted fixed production overheads of $60,000 for the period, based on 12,000 units at 2 labour hours per unit. Actual fixed ov…
- Brandt plc budgeted to make 1,000 units, with a standard of 2 labour hours per unit and a variable overhead rate of $5 per hour. It actually…
- Dalton Co makes product P, with a standard of 3 labour hours per unit at $10 per hour. In March it produced 1,200 units using 3,750 hours. W…
- Budgeted fixed production overheads were $40,000 for a budgeted output of 5,000 units, absorbed on a per-unit basis. Actual output was 4,600…