ACCA Strategic Professional · Strategic Business Leader · Leading and managing projects
During a bank's core systems upgrade, the project team has entered a phase of open disagreement. Two senior analysts challenge the approach, factions have formed and progress has slowed, although the members are committed to the project goal. Which action best reflects effective project leadership at this point?
The team is in Tuckman's storming stage, so the leader should facilitate the conflict constructively. This means clarifying roles, agreeing norms and decision-making processes, and encouraging open debate, which helps the team progress towards norming rather than suppressing disagreement or ignoring it.
- AFacilitate the conflict constructively, clarifying roles and agreeing working norms and decision processesCorrect
- BRemove the two analysts immediately to restore harmony
- CIgnore the disagreement because the team will resolve it unaided
- DImpose a strict directive style and prohibit further challenge
Explanation
This is the storming stage, where conflict over approach and roles is normal. The leader should coach and facilitate, helping establish norms so the team moves to norming. Suppressing challenge or ignoring it risks unresolved tension, and removing members loses expertise and may restart the cycle.
Did you get it right without looking?
One question tells you little. A timed set on Leading and managing projects shows your real accuracy, how long you take and where you lose marks.
More Leading and managing projects questions
- Marisol Retail is implementing a new customer data platform. A senior director, Mr Okafor, strongly influences budget decisions but has show…
- Dunmore Council plans a new digital services portal. During initiation, the project manager lists everyone affected by or able to influence …
- Brightwell Renewables is planning a solar farm build. The project manager has divided the project into deliverables (site preparation, panel…
- Marlow Council is planning a new public leisure centre. The sponsor insists on a fixed opening date and a fixed budget, but the stakeholders…
- Harlow Retail plans to replace its stock system. Senior managers agree the project is wanted, but store managers, the finance team and IT ea…
- Orlin Construction is building a hospital under a fixed-price contract. Midway, the client requests several additional features without form…