ACCA Strategic Professional · Strategic Business Leader · Leading and managing projects
Dunmore Council plans a new digital services portal. During initiation, the project manager lists everyone affected by or able to influence the project, then ranks them by power and interest to decide how much engagement each needs. Which technique is being applied, and what does it primarily support at this stage?
This is stakeholder analysis using a power/interest grid. At initiation it identifies who can affect or is affected by the project and sets an appropriate engagement approach for each group, helping to secure support and manage resistance, unlike scheduling or financial appraisal tools.
- AStakeholder analysis using a power/interest grid, to plan engagement and secure supportCorrect
- BCritical path analysis, to shorten the schedule
- CEarned value analysis, to measure cost variance
- DCost-benefit analysis, to calculate the net present value
Explanation
Ranking stakeholders by power and interest is Mendelow's power/interest grid, used in stakeholder analysis during initiation to determine engagement approaches and secure support. Critical path and earned value are planning and control tools for schedule and cost, and cost-benefit analysis evaluates financial viability.
Did you get it right without looking?
One question tells you little. A timed set on Leading and managing projects shows your real accuracy, how long you take and where you lose marks.
More Leading and managing projects questions
- Marisol Retail is implementing a new customer data platform. A senior director, Mr Okafor, strongly influences budget decisions but has show…
- Bramwell Co is planning a product launch project. The activities are: A (3 weeks, no predecessor), B (5 weeks, after A), C (2 weeks, after A…
- Brightwell Renewables is planning a solar farm build. The project manager has divided the project into deliverables (site preparation, panel…
- Marlow Council is planning a new public leisure centre. The sponsor insists on a fixed opening date and a fixed budget, but the stakeholders…
- Orlin Construction is building a hospital under a fixed-price contract. Midway, the client requests several additional features without form…
- Halden Bank's core banking replacement project is reported as 'green' by the project manager each month, based on her own progress reports. …