ACCA Strategic Professional · Strategic Business Leader · Leading and managing projects
Marlow Council is planning a new public leisure centre. The sponsor insists on a fixed opening date and a fixed budget, but the stakeholders also want every feature on a long wish list. According to the project management 'triangle' of constraints, what is the key implication for planning?
With time and cost fixed, scope or quality must flex, because the constraints of scope, time and cost are interdependent. The sponsor and stakeholders need to prioritise features, for example using must-have versus nice-to-have, rather than expecting every constraint to be met in full.
- AAll three constraints can be fixed if the project manager works harder
- BBecause scope, time and cost are interdependent, fixing time and cost means scope or quality must flexCorrect
- CQuality is independent of the other constraints and can be fixed separately
- DOnly cost should be fixed, as time and scope adjust automatically
Explanation
Scope, time and cost (with quality at the centre) are interdependent: a change in one affects the others. If date and budget are fixed, the scope or quality must be prioritised and traded off. Fixing all of them is unrealistic.
Did you get it right without looking?
One question tells you little. A timed set on Leading and managing projects shows your real accuracy, how long you take and where you lose marks.
More Leading and managing projects questions
- Marisol Retail is implementing a new customer data platform. A senior director, Mr Okafor, strongly influences budget decisions but has show…
- Lumen Foods is launching a new product line. The project risk register shows a risk with a low probability of occurring but a catastrophic i…
- Brightwell Renewables is planning a solar farm build. The project manager has divided the project into deliverables (site preparation, panel…
- Orlin Construction is building a hospital under a fixed-price contract. Midway, the client requests several additional features without form…
- Marlow Pharma has just finished a three-year plant automation project. The board asks for a review to be held after the project's outputs ha…
- Marlow Healthcare is starting a project to replace its patient records system. Before approving funds, the board asks for a document that se…