CMA Intermediate · Operations Management and Strategic Management · Project Management, Monitoring and Control
During project monitoring, a negative cost variance (CV = EV − AC) indicates which situation?
A negative cost variance means the actual cost of the work performed exceeds its earned value, so the project is over budget. Cost variance is earned value minus actual cost; schedule position is judged separately by comparing earned value with planned value.
- AWork completed has cost less than its budgeted value
- BActual cost of work done exceeds its earned valueCorrect
- CProject is ahead of schedule
- DPlanned value exceeds earned value
Explanation
CV = EV − AC. A negative value means AC is greater than EV, so the project is over budget for the work done. Planned value versus earned value relates to schedule variance, not cost variance.
Did you get it right without looking?
One question tells you little. A timed set on Project Management, Monitoring and Control shows your real accuracy, how long you take and where you lose marks.
More Project Management, Monitoring and Control questions
- Which of the following best describes resource levelling in project scheduling?
- The critical path of a project at Kaveri Constructions consists of three activities with expected times of 10, 14 and 16 days, and variances…
- An activity has optimistic time 6 days, most likely time 9 days and pessimistic time 18 days. What is the variance of its duration under PER…
- A project has a total budget at completion (BAC) of ₹20,00,000. Earned value to date is ₹8,00,000 and actual cost is ₹10,00,000. Assuming th…
- In the project life cycle, which phase is mainly concerned with defining objectives, scope, deliverables and obtaining approval to proceed?
- A construction firm in Pune has completed building a warehouse and is now handing it over to the client, obtaining acceptance, releasing sta…