For an activity in a CPM network, the earliest start (ES) is 8 days, duration is 5 days, and the latest finish (LF) is 18 days. What is its total float?
Total float equals latest finish minus earliest start minus duration: 18 - 8 - 5 = 5 days. The activity can be delayed by 5 days without delaying project completion.
- A5 daysCorrect
- B10 days
- C3 days
- D8 days
Explanation
Total float = LF - ES - duration = 18 - 8 - 5 = 5 days. Using LF - ES (10) forgets to subtract the duration. Using 18-8-5 correctly gives 5.
Did you get it right without looking?
One question tells you little. A timed set on Project Management, Monitoring and Control shows your real accuracy, how long you take and where you lose marks.
More Project Management, Monitoring and Control questions
- In the time-cost trade-off curve for a project, as the project duration is progressively reduced by crashing, how do total direct costs and …
- A project has a budgeted cost of work scheduled (planned value) of ₹8,00,000 to date, earned value of ₹6,40,000 and actual cost of ₹7,20,000…
- Which statement about free float and total float in a CPM network is correct?
- An activity has a normal time of 10 days at a normal cost of ₹40,000 and a crash time of 6 days at a crash cost of ₹52,000. Assuming linear …
- A project has an expected duration of 40 days with a standard deviation of 4 days on its critical path. Given the normal distribution, the a…
- A construction firm in Pune has completed building a warehouse and is now handing it over to the client, obtaining acceptance, releasing sta…