For an activity in a CPM network, the earliest start (ES) is 8 days, duration is 5 days, and the latest finish (LF) is 18 days. What is its total float?

Total float equals latest finish minus earliest start minus duration: 18 - 8 - 5 = 5 days. The activity can be delayed by 5 days without delaying project completion.

  1. A5 daysCorrect
  2. B10 days
  3. C3 days
  4. D8 days

Explanation

Total float = LF - ES - duration = 18 - 8 - 5 = 5 days. Using LF - ES (10) forgets to subtract the duration. Using 18-8-5 correctly gives 5.