CS Professional · Arbitration, Mediation and Conciliation · Preparation and Execution of Arbitral Award
In a domestic arbitration between Gupta Agro Ltd and Rathi Traders, pleadings under section 23(4) were completed on 1 March 2026. No award was made by 1 March 2027. The parties agreed in writing on 20 February 2027 to extend time by the maximum period they could extend by consent. Assuming no Court order, by which date must the award be made so the tribunal's mandate does not terminate?
The award must be made by 1 September 2027. The twelve months from completion of pleadings ended on 1 March 2027, and parties can extend by consent only up to a further six months. Beyond that the mandate terminates unless the Court extends the period.
- A1 September 2027Correct
- B1 March 2028
- C1 June 2027
- D31 December 2027
Explanation
Under section 29A(1) the award is due within twelve months of completion of pleadings, that is 1 March 2027. Section 29A(3) lets the parties extend by consent for a further period not exceeding six months, giving 1 September 2027. Under section 29A(4) the mandate terminates after that unless the Court has extended the time. The 1 March 2028 option wrongly adds twelve months.
Did you get it right without looking?
One question tells you little. A timed set on Preparation and Execution of Arbitral Award shows your real accuracy, how long you take and where you lose marks.
More Preparation and Execution of Arbitral Award questions
- A tribunal seated at Hyderabad by agreement between Desai Motors Ltd and Khan Auto Parts passes an award that carries no signature date and …
- In an arbitration between Mehta Pharma and Rao Logistics, Mehta Pharma succeeds on two of three claims, and Rao Logistics had refused a reas…
- Mehta Exports Ltd and Sundaram Traders agreed in their arbitration clause that the tribunal need not give reasons for its award. The sole ar…
- In a domestic arbitration, pleadings under section 23(4) were completed on 1 April 2025. The parties consented to extend the time for the aw…
- A three-member tribunal sitting in Pune decides a dispute between Kaveri Textiles Ltd and Sahyadri Dyes Pvt Ltd. Two arbitrators sign the aw…
- A tribunal awards Rs 40,00,000 to Veena Constructions against Omkar Infra. The award is silent on post-award interest and the parties have n…