CMA Final · Strategic Cost Management · Linear Programming
In a maximisation LP for Bharat Tools, the constraint x + 2y ≤ 10 for machine hours is converted to standard form for the simplex method. Which treatment is correct?
A less-than-or-equal-to constraint is converted by adding a non-negative slack variable, giving x + 2y + s = 10. The slack represents unused machine hours. Surplus and artificial variables belong to greater-than-or-equal-to constraints, so they are not required here.
- ASubtract a surplus variable and add an artificial variable
- BAdd a slack variable: x + 2y + s = 10, s ≥ 0Correct
- CAdd a slack variable: x + 2y - s = 10, s ≥ 0
- DAdd an artificial variable only, with a profit coefficient of zero
Explanation
A 'less than or equal to' constraint is converted to an equation by adding a non-negative slack variable representing unused machine hours. Surplus and artificial variables are used for 'greater than or equal to' or equality constraints. Subtracting the slack, as in the third option, would be wrong in sign.
Did you get it right without looking?
One question tells you little. A timed set on Linear Programming shows your real accuracy, how long you take and where you lose marks.
More Linear Programming questions
- A hostel mess in Pune wants to minimise the cost Z = 3x + 4y (Rs) of a mix of two foods. The nutrient constraints are x + y ≥ 10 and x + 3y …
- Sundaram Foods maximises Z = 3x + 2y subject to x + y ≤ 4, x + 3y ≤ 6, x ≤ 3, x, y ≥ 0. Using the optimal solution, which statement is corre…
- Kaveri Tools Ltd maximises Z = 50x + 40y (Rs contribution) from products A and B. The constraints are machine hours 2x + y ≤ 100, labour hou…
- A cattle-feed unit blends two ingredients P and Q to minimise cost C = 6p + 8q (₹ per batch). Each batch must satisfy protein 2p + q ≥ 10 an…
- Kaveri Feeds Ltd minimises cost Z = 6x + 8y (₹) subject to 2x + y ≥ 12, x + 2y ≥ 12, x + y ≥ 9 and x, y ≥ 0. At the optimal solution, what i…
- Ganga Plastics maximises profit Z = cA·A + 50B, where machine hours 3A + 2B ≤ 120 and labour hours A + 2B ≤ 80, with A, B ≥ 0. With cA = 40,…