CMA Final · Strategic Cost Management · Linear Programming
In the final simplex table of a maximisation problem for Rao Textiles, the Zj - Cj entry under the slack variable of the cutting-hours constraint is 7. What does this indicate?
It indicates a shadow price of Rs 7 per cutting hour. The resource is fully used, and each additional hour of capacity would increase total profit by Rs 7 within the feasible range of the optimal basis.
- ACutting hours are in surplus by 7 hours
- BProfit rises by Rs 7 for each extra cutting hour, the shadow priceCorrect
- CProfit falls by Rs 7 for each extra cutting hour
- DCutting hours cost Rs 7 more than the budgeted rate
Explanation
In the optimal table, the Zj - Cj value under a slack variable is the shadow price of that resource, the marginal increase in objective value per extra unit. A positive value means the resource is scarce and fully used, so extra hours raise profit by Rs 7, not lower it.
Did you get it right without looking?
One question tells you little. A timed set on Linear Programming shows your real accuracy, how long you take and where you lose marks.
More Linear Programming questions
- A hostel mess in Pune wants to minimise the cost Z = 3x + 4y (Rs) of a mix of two foods. The nutrient constraints are x + y ≥ 10 and x + 3y …
- A Nashik feed mill minimises cost C = 6x + 8y (₹ per unit) subject to 2x + y ≥ 12, x + 2y ≥ 12, x, y ≥ 0. What is the minimum cost?
- Sundaram Foods maximises Z = 3x + 2y subject to x + y ≤ 4, x + 3y ≤ 6, x ≤ 3, x, y ≥ 0. Using the optimal solution, which statement is corre…
- Kaveri Tools Ltd maximises Z = 50x + 40y (Rs contribution) from products A and B. The constraints are machine hours 2x + y ≤ 100, labour hou…
- A cattle-feed unit blends two ingredients P and Q to minimise cost C = 6p + 8q (₹ per batch). Each batch must satisfy protein 2p + q ≥ 10 an…
- Kaveri Feeds Ltd minimises cost Z = 6x + 8y (₹) subject to 2x + y ≥ 12, x + 2y ≥ 12, x + y ≥ 9 and x, y ≥ 0. At the optimal solution, what i…