For a contract with a notional profit of Rs 5,00,000, work certified is Rs 36,00,000 and contract price Rs 40,00,000 (so 90% complete). Cash received is Rs 32,40,000. Using the formula notional profit x cash received / contract price, what profit is transferred to the Profit and Loss Account?
Rs 4,05,000 is transferred. For a nearly complete contract, the estimated total profit is not used here; the stated formula multiplies notional profit Rs 5,00,000 by cash received over contract price, 32,40,000/40,00,000 = 81%, giving Rs 4,05,000.
- ARs 4,05,000Correct
- BRs 4,50,000
- CRs 5,00,000
- DRs 3,60,000
Explanation
For contracts 90% or more complete, profit = notional profit x cash received / contract price = 5,00,000 x 32,40,000 / 40,00,000 = 4,05,000. Rs 4,50,000 wrongly uses cash/work certified (90%).
Did you get it right without looking?
One question tells you little. A timed set on Contract Costing shows your real accuracy, how long you take and where you lose marks.
More Contract Costing questions
- Ind AS 115 (Revenue from Contracts with Customers) is applied to construction contracts by companies following Ind AS. Which statement refle…
- Shree Infra Ltd. has a contract with plant costing ₹8,00,000 at the start of the year. Plant is depreciated at 10% p.a. on cost. The plant w…
- Materials costing Rs 2,00,000 were sent to a contract site and at the year end Rs 15,000 of materials were lost by theft and Rs 25,000 of ma…
- In contract costing, each contract is treated as a separate cost unit mainly because:
- A contract of ₹80,00,000 is 50% complete. Cost to date is ₹36,00,000, work certified is ₹40,00,000 and work uncertified is carried at cost o…
- In contract costing, 'work certified' means: