CA Intermediate · Cost and Management Accounting · Job Costing
In job costing, which document is used to accumulate the costs of materials, labour and overheads for one specific customer order, and is later used to determine the profit or loss on that job?
The job cost sheet is the document used. It is opened for each job and accumulates direct materials, direct labour, direct expenses and absorbed overheads, so the total cost, and the profit or loss on that job, can be determined once the job is completed.
- ABill of materials
- BJob cost sheetCorrect
- CMaterial requisition note
- DGoods received note
Explanation
A job cost sheet is opened for each job and records direct materials, direct labour, direct expenses and absorbed overheads. A bill of materials only lists the materials needed, and a requisition note records a single issue of materials. A goods received note records receipt of purchased goods.
Did you get it right without looking?
One question tells you little. A timed set on Job Costing shows your real accuracy, how long you take and where you lose marks.
More Job Costing questions
- Verma Engineering completed Job K-9 with total cost of ₹2,40,000, including factory overheads absorbed at a predetermined rate of ₹40 per ma…
- Sharma Fabricators worked on Job J-21. Direct materials were Rs 48,000 and direct wages Rs 30,000 (1,500 labour hours at Rs 20 per hour). Fa…
- Mehta Engineers quotes prices at cost plus 25% profit on selling price. The cost of Job 31 is estimated at Rs 1,80,000. What quotation price…
- Surya Printers uses a predetermined overhead rate based on machine hours. Budgeted overheads were Rs 9,60,000 for 12,000 machine hours. Actu…
- Anand Interiors completed a job with a cost of Rs 1,20,000. During production, abnormal spoilage specific to a customer's special instructio…
- Sharma Fabricators uses a machine-hour overhead rate. Budgeted factory overheads for the year are Rs 7,20,000 and budgeted machine hours are…