Gupta Printers quotes jobs at cost plus 25% on selling price. Job P-7 has direct material Rs 24,000, direct labour Rs 16,000 and overheads absorbed at 50% of direct labour. What is the quoted price?
The quoted price is Rs 64,000. Total cost is Rs 48,000, and since profit is 25% of selling price, cost is 75% of price, giving 48,000 divided by 0.75. Adding 25% on cost would wrongly give Rs 60,000.
- ARs 60,000Correct
- BRs 62,500
- CRs 64,000
- DRs 75,000
Explanation
Overheads = 50% of 16,000 = Rs 8,000. Cost = 24,000 + 16,000 + 8,000 = Rs 48,000. Profit is 25% of selling price, so cost is 75% of price. Price = 48,000/0.75 = Rs 64,000. Check: 25% of 64,000 = 16,000 and 64,000 - 16,000 = 48,000. So the answer is Rs 64,000 (option index 2); the 25% on cost figure of Rs 60,000 is the distractor.
Did you get it right without looking?
One question tells you little. A timed set on Job Costing shows your real accuracy, how long you take and where you lose marks.
More Job Costing questions
- Gupta Metals' Job G-12 has direct materials ₹30,000, direct labour ₹18,000 (900 hours at ₹20) and factory overheads absorbed on labour hours…
- Kavya Engineering completes Job 77 for which the price quoted was Rs 1,20,000, fixed at cost plus 20% on cost. Actual material was Rs 40,000…
- In a job costing system, a firm quotes prices to customers by adding a fixed percentage margin on the total cost of each job. Which document…
- Sharma Engineering absorbs factory overheads on direct labour hours. Budgeted factory overheads for the year are Rs 6,00,000 and budgeted di…
- In job costing, which document is normally used to accumulate the material, labour and overhead costs of a specific job and serves as the ba…
- Verma Printers quotes jobs at cost plus 25% profit on selling price. Job P-7 has a total cost of Rs 90,000. What quotation price should be g…