In Mendelow's power-interest matrix, which strategy is recommended for a stakeholder with high power but low interest?

A stakeholder with high power but low interest should be kept satisfied. Their power means they could affect the organisation if they became concerned, but their low interest means they need not be heavily involved or consulted on every issue.

  1. AKeep satisfiedCorrect
  2. BKeep informed
  3. CMinimal effort

Explanation

High-power, low-interest stakeholders (Box B) should be kept satisfied so that their interest is not aroused and they do not use their power against the organisation. Keep informed is for low power, high interest stakeholders. Minimal effort is for low power, low interest stakeholders.

Did you get it right without looking?

One question tells you little. A timed set on Stakeholders in business organisations shows your real accuracy, how long you take and where you lose marks.

More Stakeholders in business organisations questions