In the time-cost trade-off curve for a project, as the project duration is progressively reduced by crashing, how do total direct costs and total indirect costs typically behave?
Direct costs rise and indirect costs fall as duration is shortened. Crashing needs extra resources, overtime and expediting, which add direct cost, while a shorter project incurs fewer periods of overheads. The optimum project duration is where total cost is minimum.
- ADirect costs fall and indirect costs rise
- BDirect costs rise and indirect costs fallCorrect
- CBoth direct and indirect costs rise
- DBoth direct and indirect costs remain unchanged
Explanation
Crashing needs extra resources such as overtime and additional labour, so direct costs increase as duration shortens. Overheads and other time-related indirect costs accrue per period, so a shorter project reduces them. The optimum duration lies where their sum, the total cost, is lowest.
Did you get it right without looking?
One question tells you little. A timed set on Project Management, Monitoring and Control shows your real accuracy, how long you take and where you lose marks.
More Project Management, Monitoring and Control questions
- In project crashing under the time-cost trade-off method, which activities should be considered first for shortening the project duration?
- A construction firm in Pune has completed building a warehouse and is now handing it over to the client, obtaining acceptance, releasing sta…
- Which of the following best describes resource levelling in project scheduling?
- The critical path of a project at Kaveri Constructions consists of three activities with expected times of 10, 14 and 16 days, and variances…
- Which feature best distinguishes a project from routine operations in an organisation?
- An activity has optimistic time 6 days, most likely time 9 days and pessimistic time 18 days. What is the variance of its duration under PER…