Kaveri Engineering recorded that the first unit of a job took 200 hours, and the first 4 units together took 512 hours. Assuming a cumulative average-time learning curve, what is the learning rate?

The learning rate is 80%. The average time for 4 units is 128 hours (512 ÷ 4) against 200 hours for the first unit. Four units involve two doublings, so r² = 128/200 = 0.64, and the rate per doubling is the square root, 0.8.

  1. A64%
  2. B75%
  3. C80%Correct
  4. D85%

Explanation

The cumulative average time for 4 units is 512 / 4 = 128 hours. Going from 1 to 4 units is two doublings, so 200 × r² = 128, which gives r² = 0.64 and r = 0.8. The 64% option is r², the effect of two doublings, not the rate per doubling.