CA Intermediate · Cost and Management Accounting · Standard Costing
Kaveri Textiles has a standard of 5 hours per unit at ₹40 per hour. In a month it produced 1,000 units. Hours paid were 5,500 at ₹42 per hour, of which 300 hours were idle because of a power failure. What are the labour efficiency variance and idle time variance?
Efficiency variance is ₹8,000 adverse because 5,200 hours were worked against 5,000 standard hours at ₹40. Idle time variance is ₹12,000 adverse, being 300 idle hours at the standard rate of ₹40. Both are valued at the standard rate.
- AEfficiency ₹8,000 Adverse; Idle time ₹12,600 Adverse
- BEfficiency ₹8,000 Adverse; Idle time ₹12,000 AdverseCorrect
- CEfficiency ₹10,000 Adverse; Idle time ₹12,000 Adverse
- DEfficiency ₹8,400 Adverse; Idle time ₹12,600 Adverse
Explanation
Standard hours for actual output = 1,000 × 5 = 5,000. Actual hours worked = 5,500 − 300 = 5,200. Efficiency variance = (5,000 − 5,200) × 40 = ₹8,000 A. Idle time variance = 300 × standard rate 40 = ₹12,000 A. Option 1 values idle time at the actual rate of ₹42, which is wrong. Option 3 uses paid hours (5,500) for efficiency, ignoring idle time.
Did you get it right without looking?
One question tells you little. A timed set on Standard Costing shows your real accuracy, how long you take and where you lose marks.
More Standard Costing questions
- Standard Costing: Which one of the following best describes a 'basic standard' in standard costing?
- Standard sales of a firm were 2,000 units at a standard selling price of Rs 100 and a standard cost of Rs 70 per unit. Actual sales were 1,8…
- Which statement about a standard that is set at the level of 'ideal standard' is correct?
- Standard cost per unit of a product: material Rs 120, labour Rs 60. Fixed overhead is budgeted at Rs 3,00,000 for 10,000 units. Actual outpu…
- In standard costing, a standard that is set on the assumption of ideal operating conditions, with no allowance for normal wastage, machine b…
- Anand Engineering absorbs variable overheads at Rs 20 per labour hour. Budgeted output was 2,400 units at 5 hours per unit. Actual output wa…