Which statement about a standard that is set at the level of 'ideal standard' is correct?
An ideal standard assumes perfect conditions with no wastage, idle time or inefficiency, so it is rarely achievable in practice. Standards allowing for normal losses and delays are attainable standards, and those based on past averages are historical standards.
- AIt assumes no wastage, no idle time and maximum efficiency, so it is rarely achievableCorrect
- BIt is based on the average of past actual performance
- CIt allows for normal losses and normal idle time
- DIt is the standard expected to be attained under current conditions
Explanation
An ideal standard is set assuming the best possible conditions, with no wastage, breakdowns or idle time. Hence it is seldom attained. Standards allowing normal losses are attainable (normal) standards.
Did you get it right without looking?
One question tells you little. A timed set on Standard Costing shows your real accuracy, how long you take and where you lose marks.
More Standard Costing questions
- Kaveri Components budgeted to make 5,000 units of a product in a month with standard labour of 3 hours per unit at Rs 80 per hour. Actual pr…
- Bharat Chemicals uses a standard mix for 100 kg of output: 60 kg of A at Rs 50 per kg and 50 kg of B at Rs 40 per kg (standard loss 10 kg). …
- Kaveri Auto Components fixes a standard of 4 labour hours per unit at Rs 150 per hour. In March it produced 1,500 units. Labour hours paid w…
- Standard Costing: Which one of the following best describes a 'basic standard' in standard costing?
- Standard sales of a firm were 2,000 units at a standard selling price of Rs 100 and a standard cost of Rs 70 per unit. Actual sales were 1,8…
- Standard cost per unit of a product: material Rs 120, labour Rs 60. Fixed overhead is budgeted at Rs 3,00,000 for 10,000 units. Actual outpu…