ACCA Applied Knowledge · Management Accounting · Variance calculations and analysis

Dunmore Co absorbs variable overheads at $2.50 per labour hour. The standard time is 3 hours per unit. In May it produced 1,500 units using 4,700 labour hours. What is the variable overhead efficiency variance?

The efficiency variance is $500 adverse. The 1,500 units should have taken 4,500 hours, but 4,700 hours were worked. The 200 excess hours multiplied by the standard variable overhead rate of $2.50 per hour give an adverse variance of $500.

  1. A$500 adverseCorrect
  2. B$500 favourable
  3. C$1,250 adverse
  4. D$450 adverse

Explanation

Standard hours for actual output = 1,500 × 3 = 4,500. Actual hours were 4,700, so 200 hours more were used. 200 × $2.50 = $500 adverse. A favourable answer ignores that more hours than standard were used.

Did you get it right without looking?

One question tells you little. A timed set on Variance calculations and analysis shows your real accuracy, how long you take and where you lose marks.

More Variance calculations and analysis questions