ACCA Strategic Professional · Strategic Business Leader · Leading and managing projects
Lumen Foods is launching a new product line. The project risk register shows a risk with a low probability of occurring but a catastrophic impact on safety if it does, such as contamination at the pilot plant. Which response is most appropriate under a typical risk matrix approach?
The risk deserves senior attention with preventive controls and contingency or transfer arrangements. A risk matrix weighs impact as well as likelihood, so a catastrophic safety consequence warrants active management even when probability is low. Ignoring it, monitoring it only at project close or delegating it to junior staff is inadequate.
- AIgnore it because the probability is low
- BAccept it and monitor it only at the project close
- CGive it senior attention with preventive controls and contingency or transfer arrangements because of the severity of impactCorrect
- DDelegate it to the most junior team member to track
Explanation
Risk matrices consider both probability and impact, and low-probability, high-impact risks require preventive controls and contingency plans or transfer such as insurance. Ignoring it relies on probability alone. Monitoring only at close and junior delegation provide inadequate control.
Did you get it right without looking?
One question tells you little. A timed set on Leading and managing projects shows your real accuracy, how long you take and where you lose marks.
More Leading and managing projects questions
- Bramwell Co is planning a product launch project. The activities are: A (3 weeks, no predecessor), B (5 weeks, after A), C (2 weeks, after A…
- Marisol Retail is implementing a new customer data platform. A senior director, Mr Okafor, strongly influences budget decisions but has show…
- Brightwell Renewables is planning a solar farm build. The project manager has divided the project into deliverables (site preparation, panel…
- Halden Bank's core banking replacement project is reported as 'green' by the project manager each month, based on her own progress reports. …
- Marlow Council is planning a new public leisure centre. The sponsor insists on a fixed opening date and a fixed budget, but the stakeholders…
- Orlin Construction is building a hospital under a fixed-price contract. Midway, the client requests several additional features without form…