Marlow Pharma has just finished a three-year plant automation project. The board asks for a review to be held after the project's outputs have been in operation for nine months, mainly to check whether the promised productivity gains have been achieved and to inform the approval of future projects. Which type of review is this?
This is a post-completion review. It takes place after the project outputs have been operating for a period, compares actual benefits such as productivity gains with those promised in the business case, and records lessons to improve future project selection and management. Closure or milestone reviews happen earlier and cannot assess realised benefits.
- AA post-completion review (post-implementation benefits review) focused on outcomes and lessons for future projectsCorrect
- BA project initiation review carried out to confirm the business case before funding is approved
- CA milestone review to decide whether the project should continue to the next stage
- DA post-project review held at closure to hand over deliverables and release the team
Explanation
A review carried out after the outputs have been operating, checking whether benefits were achieved and capturing lessons for future projects, is a post-completion review. A closure or handover review occurs at the end of the project and cannot measure benefits that only emerge later. Milestone and initiation reviews occur earlier in the lifecycle.
Did you get it right without looking?
One question tells you little. A timed set on Leading and managing projects shows your real accuracy, how long you take and where you lose marks.
More Leading and managing projects questions
- Brightwell Renewables is planning a solar farm build. The project manager has divided the project into deliverables (site preparation, panel…
- Marlow Council is planning a new public leisure centre. The sponsor insists on a fixed opening date and a fixed budget, but the stakeholders…
- Dunmore Council plans a new digital services portal. During initiation, the project manager lists everyone affected by or able to influence …
- Orlin Construction is building a hospital under a fixed-price contract. Midway, the client requests several additional features without form…
- Harlow Retail plans to replace its stock system. Senior managers agree the project is wanted, but store managers, the finance team and IT ea…
- Marlow Healthcare is starting a project to replace its patient records system. Before approving funds, the board asks for a document that se…