Marlow Engineering's finance director says the budget process is mainly used to gain managers' commitment to targets. Managers set their own budgets and discuss them with superiors before approval. Which feature of this system is most likely to follow from this approach, compared with an imposed budget?
Participative budgeting creates a greater risk of budgetary slack. Managers who set their own targets may understate revenue or overstate costs to make targets easier. Imposed budgets give stronger strategic alignment and speed, but participation tends to improve commitment and use of local knowledge.
- AGreater risk of budgetary slack being built inCorrect
- BCloser alignment of budgets with the top management's strategy
- CFaster preparation of the budget
- DLess need for negotiation between levels
Explanation
Participative budgeting improves motivation, commitment and use of local knowledge, but gives managers the opportunity to build in slack by understating revenue or overstating costs. The other options are advantages of imposed budgets: strategic alignment, speed and less negotiation.
Did you get it right without looking?
One question tells you little. A timed set on Budgetary planning and control shows your real accuracy, how long you take and where you lose marks.
More Budgetary planning and control questions
- Harlow Components uses an annual fixed budget agreed in November. By June, market conditions have changed sharply, yet managers are still ju…
- Brandt Plc is considering how difficult to make budget targets. Research on motivation suggests which targets are most likely to maximise pe…
- Orlin Group uses a budget-constrained evaluation style: managers are judged mainly on meeting the annual cost budget, with severe consequenc…
- Norvik Services is considering moving to a Beyond Budgeting model. Which of the following changes is most consistent with that philosophy?
- Orion Ltd budgeted 2,000 labour hours at $15 to make 1,000 units. Actual output was 1,100 units using 2,300 hours, paid at $14.50 per hour. …
- Halden Co budgets for a product with a selling price of 50 per unit. Demand is uncertain. The unit variable cost is 30 and the batch must be…