ACCA Strategic Professional · Advanced Performance Management · Budgetary planning and control
Marlow Ltd budgeted 8,000 units with variable overhead of $5 per unit and fixed overhead of $40,000. Actual output was 9,000 units and actual total overhead was $88,000. What is the overhead variance against the flexed budget?
The variance is $3,000 adverse. The flexed budget for 9,000 units is $45,000 variable plus $40,000 fixed, totalling $85,000. Actual overhead of $88,000 is $3,000 higher. Comparing with the original $80,000 budget would wrongly include a volume effect.
- A$3,000 adverseCorrect
- B$3,000 favourable
- C$8,000 adverse
- D$5,000 adverse
Explanation
Flexed budget = 9,000 x $5 + $40,000 = $85,000. Actual $88,000 exceeds this by $3,000, so adverse. Using the original budget of $80,000 gives $8,000 adverse, which wrongly includes the volume effect.
Did you get it right without looking?
One question tells you little. A timed set on Budgetary planning and control shows your real accuracy, how long you take and where you lose marks.
More Budgetary planning and control questions
- Orchard Foods replaces its traditional incremental budget with an approach where each manager must justify every activity's cost from zero e…
- A divisional manager receives a monthly report showing a large adverse materials price variance caused by a supplier price rise imposed by h…
- Dalton Retail's budgeted sales were 5,000 units at $20, with a standard contribution of $8 per unit. Actual sales were 4,600 units at $21. V…
- Tarn Engineering evaluates plant managers using a budget-constrained style, so a manager is judged solely on meeting the budgeted cost every…
- Quorra Software develops products in a fast-changing, innovative sector. Its CEO is considering replacing the traditional annual budget with…
- Wexley Logistics prepares a budget for delivery costs at a planned 100,000 deliveries. Actual deliveries were 90,000. Budgeted cost is $300,…