CA Intermediate · Cost and Management Accounting · Employee Cost and Direct Expenses
Which of the following is an example of idle time in employee cost accounting?
Time lost because of a power failure is idle time, since workers are paid but cannot produce anything. Rework, machine set-up and overtime all involve work actually being done, so they are not idle time.
- ATime lost by workers because of a power failure at the factoryCorrect
- BTime spent by workers on rework of defective units caused by poor workmanship
- CTime spent by a machine operator in setting up the machine for a new job
- DOvertime put in by workers to complete a rush order
Explanation
Idle time is paid time during which workers produce nothing because of causes such as power failure, machine breakdown or waiting for material. Rework time is a cost of abnormal or normal spoilage and rework, not idle time. Set-up time is productive preparatory work and overtime is extra hours worked, so neither is idle time.
Did you get it right without looking?
One question tells you little. A timed set on Employee Cost and Direct Expenses shows your real accuracy, how long you take and where you lose marks.
More Employee Cost and Direct Expenses questions
- Under the Halsey premium plan, a worker at Pune Tools is paid Rs 50 per hour. The time allowed for a job is 40 hours and the worker complete…
- In a factory, the cost of idle time arising from a normal power failure of 2 hours per month is treated in cost accounting as follows:
- Under Rowan plan, a worker at Sahyadri Metals has a standard time of 20 hours, a rate of Rs 60 per hour and takes 15 hours for a job. Total …
- Kaveri Engineering uses the Rowan plan. Standard time for a job is 50 hours, actual time taken is 40 hours, and the rate is Rs 80 per hour. …
- Which of the following is treated as an abnormal idle time cost and is therefore charged to the Costing Profit and Loss Account rather than …
- Under the Rowan plan, a worker at Sundaram Tools has a time allowed of 40 hours and takes 30 hours, at ₹80 per hour. What is the total earni…