CMA Final · Strategic Cost Management · Activity Based Cost Management
Meera Foods Ltd has a distribution activity pool of Rs 9,00,000. The practical capacity is 6,000 deliveries, but only 4,500 deliveries are expected this year. Under ABC with the cost driver rate based on practical capacity, what is the cost of unused capacity for the year?
The cost of unused capacity is Rs 2,25,000. The rate based on practical capacity is Rs 150 per delivery, and 1,500 deliveries of capacity remain unused, so unused cost is 1,500 multiplied by Rs 150.
- ARs 1,50,000
- BRs 2,25,000Correct
- CRs 3,00,000
- DRs 4,50,000
Explanation
The rate on practical capacity = 9,00,000 / 6,000 = Rs 150 per delivery. Unused capacity = 6,000 - 4,500 = 1,500 deliveries. Cost of unused capacity = 1,500 x 150 = Rs 2,25,000. Rs 1,50,000 wrongly uses a rate of Rs 100.
Did you get it right without looking?
One question tells you little. A timed set on Activity Based Cost Management shows your real accuracy, how long you take and where you lose marks.
More Activity Based Cost Management questions
- Ganga Electronics has two products. Overhead pools: setups Rs 4,00,000 (driver: 100 setups) and packing Rs 2,40,000 (driver: 1,200 packing o…
- Kaveri Components Ltd has a quality inspection cost pool of Rs 3,60,000 with a cost driver of number of inspections, total 1,200 inspections…
- Under activity based costing, the cost of 'product design modification', which is incurred for each product line regardless of the number of…
- Under activity based management, a non-value-added activity such as rework of defective output is best handled by:
- Kaveri Textiles has a material-handling pool of Rs 4,80,000 and uses the number of material movements as the driver. Budgeted movements are …
- In an activity based costing system, which of the following is the best example of a batch-level activity?