CMA Final · Strategic Cost Management · Activity Based Cost Management
In an activity based costing system, which of the following is the best example of a batch-level activity?
Machine setup for each production run is a batch-level activity because its cost is incurred each time a batch is processed, irrespective of the number of units in the batch. Unit-level, facility-level and product-sustaining activities behave differently.
- AMachine setup for each production runCorrect
- BMachine hours used on each unit
- CPlant security and building maintenance
- DDesign of a new product variant
Explanation
Batch-level activities are performed once for each batch regardless of the number of units in it; setups are the classic example. Machine hours on each unit is a unit-level activity, plant security is facility-level, and product design is product-sustaining.
Did you get it right without looking?
One question tells you little. A timed set on Activity Based Cost Management shows your real accuracy, how long you take and where you lose marks.
More Activity Based Cost Management questions
- Dhruv Engineering uses ABC. Its quality inspection pool is Rs 4,80,000, expected to involve 2,400 inspection hours. A customised order needs…
- Ganga Foods Ltd identifies the following for the packing activity: cost pool ₹1,80,000, practical capacity 9,000 packing runs, actual runs 6…
- Under activity based cost management, an activity of 'rework of defective output' is classified as non-value-adding. Which action best refle…
- Yamuna Auto Ltd has an ordering activity pool of Rs 2,40,000 and 800 purchase orders are placed, of which 200 relate to a customer-specific …
- Ganga Electronics has two products. Overhead pools: setups Rs 4,00,000 (driver: 100 setups) and packing Rs 2,40,000 (driver: 1,200 packing o…
- Kaveri Components Ltd has a quality inspection cost pool of Rs 3,60,000 with a cost driver of number of inspections, total 1,200 inspections…