Under activity based costing, the cost of 'product design modification', which is incurred for each product line regardless of the number of units or batches, is classified as which level of activity?

It is a product-sustaining activity. Design modification supports a particular product line irrespective of units made or batches run, whereas unit-level costs vary with each unit, batch-level costs with batches, and facility-level costs benefit the entire plant.

  1. AUnit-level activity
  2. BBatch-level activity
  3. CProduct-sustaining activityCorrect
  4. DFacility-sustaining activity

Explanation

Product-sustaining activities support a specific product line, such as design and engineering changes, independent of volume or batches. Batch-level costs depend on batches, and facility-sustaining costs support the whole plant.

Did you get it right without looking?

One question tells you little. A timed set on Activity Based Cost Management shows your real accuracy, how long you take and where you lose marks.

More Activity Based Cost Management questions