CMA Final · Strategic Financial Management · Evaluation of Risky Proposals for Investment Decisions
Meera Industries has a project with expected NPV of Rs 40 lakh and standard deviation of NPV of Rs 25 lakh. Assuming NPV is normally distributed, what is the probability that the NPV will be negative? (Area under the normal curve from 0 to z=1.60 is 0.4452.)
The probability of a negative NPV is 5.48%. The standardised value is (0 - 40)/25 = -1.60, the area from the mean to that point is 0.4452, so the tail beyond it is 0.5 - 0.4452 = 0.0548.
- A5.48%Correct
- B4.52%
- C44.52%
- D94.52%
Explanation
z = (0 - 40)/25 = -1.60. Probability NPV < 0 = 0.5 - 0.4452 = 0.0548, i.e. 5.48%. 44.52% is only the area between the mean and zero, not the tail. 94.52% adds instead of subtracting and gives the probability of a positive NPV on the wrong side.
Did you get it right without looking?
One question tells you little. A timed set on Evaluation of Risky Proposals for Investment Decisions shows your real accuracy, how long you take and where you lose marks.
More Evaluation of Risky Proposals for Investment Decisions questions
- A project of Kaveri Engineering has an initial outlay of Rs 1,00,000 and a single cash inflow at the end of year 1 with the following probab…
- A project has three possible NPV outcomes (₹ lakh): −2 with probability 0.2, 4 with probability 0.5 and 10 with probability 0.3. The coeffic…
- Meenakshi Textiles is evaluating a project whose cash flows are uncertain. Its normal required return is 12% and the project is judged under…
- A project costs Rs 1,00,000 now and gives a certain-equivalent cash flow of Rs 60,000 at the end of each of the next 2 years. The risk-free …
- A project of Kaveri Industries has an initial outlay of Rs 2,00,000 and a single inflow after one year. The inflow is Rs 1,00,000 with proba…
- A project of Arjun Auto has a base-case NPV of Rs 12 lakh. The present value of annual sales-linked inflows is Rs 80 lakh. Management wants …