CA Intermediate · Advanced Accounting · AS 16 Borrowing Costs
Raghavendra Textiles Ltd is reviewing which of its assets are qualifying assets under AS 16 for capitalising borrowing costs. Which of the following is a qualifying asset?
The captive power plant taking about 18 months to build is the qualifying asset. AS 16 treats an asset as qualifying when it necessarily takes a substantial period to get ready for its intended use or sale. Ready-to-use items, stationery and quickly sold goods need no such period.
- ATrading goods purchased on credit and sold within a week
- BA captive power plant that will take about 18 months to construct and commissionCorrect
- COffice stationery bought for immediate use
- DA ready-to-use delivery van purchased from a dealer and put to use the same day
Explanation
AS 16 defines a qualifying asset as one that necessarily takes a substantial period of time to get ready for its intended use or sale. An 18-month construction of a power plant meets this. Goods sold in a week, stationery and a ready van are ready at once, so no substantial period is needed.
Did you get it right without looking?
One question tells you little. A timed set on AS 16 Borrowing Costs shows your real accuracy, how long you take and where you lose marks.
More AS 16 Borrowing Costs questions
- Sahyadri Infra Ltd. started constructing a bridge, a qualifying asset, on 1 April 2025 using a specific loan of Rs 1,20,00,000 at 10% p.a. A…
- Sundaram Infra Ltd is considering four items for the purpose of applying AS 16 Borrowing Costs. Which one is a qualifying asset?
- Malabar Constructions Ltd. was building a bridge-linked office complex, a qualifying asset. Active development was suspended for 4 months be…
- Surya Steels Ltd. took a specific term loan of ₹4,00,000 at 12% p.a. on 1 April 2025 to construct a warehouse. Construction was in progress …
- Sundaram Textiles Ltd. began constructing a new dyeing unit on 1 April 2025. It borrowed Rs 2,00,00,000 specifically for the project at 9% p…
- Meera Engineers Ltd. completed a factory building on 31 December, though some minor interior finishing remained pending, which would not pre…