ACCA Strategic Professional · Strategic Business Reporting (International) · Provisions, contingencies and events after the reporting period
Orion Ltd must pay $5m in three years to clean up a site it has contaminated. Orion's pre-tax risk-free rate is 4% and its pre-tax rate reflecting risks specific to the liability, after adjusting cash flows, is 6%. The cash flow estimates already reflect the risks of the liability. Which statement about measurement under IAS 37 is correct?
Orion should discount at a pre-tax rate reflecting time value and only those liability-specific risks not already included in the cash flows, then recognise the unwinding of the discount as a finance cost. Using a rate that repeats risk adjustments would double count risk.
- ADiscount at 6% because the rate must include the risks specific to the liability even though the cash flows already allow for them
- BDiscount at a pre-tax rate reflecting the time value of money and risks not already reflected in the cash flow estimates, and unwind the discount as a finance costCorrect
- CDo not discount because the obligation is a provision for environmental damage
- DDiscount at Orion's post-tax cost of capital and unwind the discount through operating expenses
Explanation
IAS 37 requires a pre-tax discount rate reflecting current market assessments of time value of money and risks specific to the liability, excluding risks already adjusted in the cash flows, to avoid double counting. The unwinding is recognised as a borrowing cost. Option 0 double counts the risk.
Did you get it right without looking?
One question tells you little. A timed set on Provisions, contingencies and events after the reporting period shows your real accuracy, how long you take and where you lose marks.
More Provisions, contingencies and events after the reporting period questions
- Bramwell Co decides on 15 December 20X5 to close a division. A detailed formal plan was approved by the board, but no announcement was made …
- Orion plc is claiming $2m compensation from a supplier for defective goods. At the reporting date, Orion's lawyers say it is probable that t…
- Brava plc has a 31 March 20X6 year end and the financial statements were authorised on 20 June 20X6. On 15 May 20X6 a fire destroyed a wareh…
- Zenith plc decides on 15 December 20X5 to close a factory. Detailed formal plans were approved by the board on that date, but the plan was n…
- Parent plc acquired 80% of Sub Ltd on 1 January 20X5. At the acquisition date Sub was defending a lawsuit. The fair value of the potential o…
- Orion plc has claimed $800,000 from an insurer for fire damage to a warehouse. At the reporting date the insurer has neither accepted nor re…