CA Intermediate · Cost and Management Accounting · Employee Cost and Direct Expenses
Rohan Foods pays a skilled worker Rs 50 per hour for a 40-hour week. Overtime is paid at double the normal rate. In one week the worker works 48 hours, of which 5 hours of overtime were due to a customer's urgent order for a specific job and 3 hours due to general production pressure. Treat overtime premium as per standard cost accounting practice. How much is charged directly to the urgent job for this worker's overtime?
Overtime requested by a customer for a specific job is charged directly to that job, including the premium. At double rate, 5 hours cost 5 x Rs 100 = Rs 500, made up of Rs 250 normal wages and Rs 250 premium, so Rs 500 goes to the urgent job.
- ARs 250
- BRs 500Correct
- CRs 750
- DRs 400
Explanation
When overtime is at a customer's request for a specific job, the premium is charged directly to that job. Overtime wages at double rate are Rs 100 per hour; the normal part (Rs 50) is wages, and the premium is Rs 50 per hour. For 5 hours, premium = Rs 250 and normal wages = Rs 250, so the total charged to the job is Rs 500. Rs 250 includes only the premium or only the normal part. Rs 750 mistakenly uses triple rate.
Did you get it right without looking?
One question tells you little. A timed set on Employee Cost and Direct Expenses shows your real accuracy, how long you take and where you lose marks.
More Employee Cost and Direct Expenses questions
- Kapoor Fabricators pays a worker on the Emerson efficiency system. Standard output is 50 units per day of 8 hours, day wage is Rs 640, and t…
- Sharma Tools pays a worker under the Halsey premium plan. Standard time for a job is 40 hours, time taken is 30 hours, the wage rate is Rs. …
- Sharma Fabricators pays a worker under the Rowan plan. Standard time for a job is 20 hours, the hourly rate is Rs 80, and the worker finishe…
- Which one of the following is treated as a direct expense of a job rather than as overhead?
- Rohini Textiles had the following for the month: 40 workers, each normally working 200 hours, with a time rate of Rs 90 per hour. Actual idl…
- Mehta Fabricators pays piece wages under the Halsey premium plan. Standard time for a job is 40 hours, and the worker completes it in 30 hou…