Sharma Fabricators pays a worker under the Rowan plan. Standard time for a job is 20 hours, the hourly rate is Rs 80, and the worker finishes in 15 hours. The same worker's earnings are compared with the Halsey plan at 50% sharing. By how much do the Rowan earnings differ from the Halsey earnings?
Rowan gives Rs 1,500 (Rs 1,200 wages plus a bonus of time saved over time allowed, 5/20, times time taken and rate, Rs 300). Halsey gives Rs 1,400. Rowan is therefore higher by Rs 100.
- ARowan is higher by Rs 50Correct
- BRowan is lower by Rs 50
- CRowan is higher by Rs 100
- DBoth plans give the same earnings
Explanation
Rowan: 15 x 80 = 1,200; bonus = (5/20) x 15 x 80 = 300; total 1,500. Halsey: 1,200 + 50% x 5 x 80 = 1,200 + 200 = 1,400. Difference = Rs 100 higher under Rowan. So the correct key is Rs 100 higher.
Did you get it right without looking?
One question tells you little. A timed set on Employee Cost and Direct Expenses shows your real accuracy, how long you take and where you lose marks.
More Employee Cost and Direct Expenses questions
- In a factory, the time spent by workers because of a power failure, for which they are paid wages but no production takes place, is called i…
- Gupta Engineering follows the Rowan plan. Standard time for a job is 20 hours, actual time taken is 16 hours, and the hourly rate is Rs. 80.…
- Aarav Constructions engaged a specialist contractor for a special fabrication on Job 22. The cost of a drawing design prepared by an externa…
- Mehta Textiles employs 400 workers on average during the year. During the year 28 workers left and 12 were replaced; in addition 20 new work…
- Under the Rowan plan, a worker at Sundaram Engineering has a time allowed of 20 hours, takes 15 hours, and earns Rs 60 per hour. What is the…
- Under the Halsey premium plan, a worker at Pune Tools is paid Rs 50 per hour. The time allowed for a job is 40 hours and the worker complete…