CMA Final · Strategic Cost Management · Quality Cost Management
Sundaram Auto Parts reports the following quality costs for a month (Rs. lakh): quality training 4, supplier evaluation 3, inspection of finished goods 6, product testing 5, rework 8, scrap 4, warranty claims 9, customer complaint handling 3. Total prevention plus appraisal cost is:
Prevention costs are 4 + 3 = Rs. 7 lakh and appraisal costs are 6 + 5 = Rs. 11 lakh, so the total is Rs. 18 lakh. Rework, scrap, warranty and complaint handling are failure costs and are excluded from this total.
- ARs. 18 lakhCorrect
- BRs. 12 lakh
- CRs. 21 lakh
- DRs. 15 lakh
Explanation
Prevention = training 4 + supplier evaluation 3 = 7. Appraisal = inspection 6 + testing 5 = 11. Total = 18. Rs. 12 lakh omits testing and the supplier evaluation. Rs. 21 lakh wrongly adds the customer complaint handling (external failure).
Did you get it right without looking?
One question tells you little. A timed set on Quality Cost Management shows your real accuracy, how long you take and where you lose marks.
More Quality Cost Management questions
- Which of the following is classified as an internal failure cost in a cost of quality (COQ) report?
- Gomti Textiles produces 10,000 metres of fabric daily. Of this, 8% fails inspection; 60% of failures are reworked at Rs. 25 per metre and th…
- Mehta Auto Components currently spends Rs. 4,00,000 on prevention and appraisal and incurs failure costs of Rs. 9,00,000 a year. Management …
- Himalaya Gears makes 20,000 units a year. Currently 6% of units fail in-process inspection and are scrapped at Rs. 500 each. A new process c…
- Tapti Plastics reports sales of Rs. 50,00,000 for the year. Its quality costs are prevention Rs. 2,00,000, appraisal Rs. 3,00,000, internal …
- Sundaram Pumps reports these quarterly quality figures: supplier quality training Rs. 40,000; incoming material inspection Rs. 90,000; scrap…