CMA Final · Strategic Cost Management · Quality Cost Management
Sundaram Auto Parts reports the following annual quality costs: design review Rs. 1,20,000; supplier evaluation Rs. 80,000; final inspection Rs. 2,50,000; scrap Rs. 1,50,000; rework Rs. 1,00,000; warranty claims Rs. 3,00,000; lost sales from poor reputation Rs. 2,00,000 (opportunity cost, not in books). What is the total cost of nonconformance (failure costs) including the opportunity cost?
Nonconformance cost is Rs. 8,50,000. It adds internal failure (scrap and rework, Rs. 2,50,000) to external failure (warranty Rs. 3,00,000 and lost sales Rs. 2,00,000). Design review, supplier evaluation and final inspection are conformance costs and are excluded.
- ARs. 6,50,000
- BRs. 8,50,000Correct
- CRs. 10,00,000
- DRs. 7,00,000
Explanation
Failure costs = scrap 1,50,000 + rework 1,00,000 + warranty 3,00,000 + lost sales 2,00,000 = Rs. 8,50,000. Excluding the opportunity cost gives 6,50,000. Inspection and prevention items are conformance costs.
Did you get it right without looking?
One question tells you little. A timed set on Quality Cost Management shows your real accuracy, how long you take and where you lose marks.
More Quality Cost Management questions
- Tapti Plastics reports sales of Rs. 50,00,000 for the year. Its quality costs are prevention Rs. 2,00,000, appraisal Rs. 3,00,000, internal …
- Sundaram Pumps reports these quarterly quality figures: supplier quality training Rs. 40,000; incoming material inspection Rs. 90,000; scrap…
- Narmada Pumps makes 10,000 units a year. Present quality costs: prevention Rs. 1,00,000, appraisal Rs. 1,50,000, internal failure Rs. 3,00,0…
- Sundaram Pumps reports these annual quality costs: supplier quality audits Rs. 1,20,000; warranty repairs Rs. 2,50,000; final inspection Rs.…
- Ananya Foods has sales of Rs. 50,00,000. Quality costs are prevention Rs. 1,00,000, appraisal Rs. 1,50,000, internal failure Rs. 2,00,000 an…
- Sundaram Auto Parts reports the following quality costs for a month (Rs. lakh): quality training 4, supplier evaluation 3, inspection of fin…