Sundaram Textiles Ltd agrees to deliver 500 bales of cloth to Kavya Garments on 1 March. It delivers late, and Kavya Garments loses the ordinary profit it would normally have earned from using the cloth in its usual business. Under the Indian Contract Act, which statement best describes the loss that Kavya Garments can recover?
Kavya Garments can recover loss arising naturally in the usual course from the breach, or loss both parties knew at the time of contracting would probably result. Remote or indirect losses are not recoverable, so ordinary lost profit is claimable but unusual losses are not.
- AOnly losses that arise naturally in the usual course of things from the breach, or that both parties knew would probably resultCorrect
- BEvery loss that followed from the breach, however unusual, provided it was caused by the delay
- COnly losses that can be measured exactly in rupees before the contract was signed
- DRemote and indirect losses, because the supplier is in breach
- Only the price already paid, with no allowance for lost profit
Explanation
Compensation is available for loss naturally arising in the usual course from the breach, or loss the parties knew at contract time was likely. Ordinary lost profit from usual use falls within this. Unusual losses and remote or indirect losses are excluded, so the second and fourth options are wrong.
Did you get it right without looking?
One question tells you little. A timed set on Implied terms, exclusion of liability, contractual remedies and damages shows your real accuracy, how long you take and where you lose marks.
More Implied terms, exclusion of liability, contractual remedies and damages questions
- Kavita buys a second-hand car from Rohan for ₹4,00,000. Rohan states that the car has had only one previous owner; this is a minor point whi…
- Arvind, a senior actuary, signed a valid employment contract with Zenith Life containing a clause stopping him from working for any competin…
- Meridian Re agreed to supply a reinsurance quote to Orchid General by a fixed date, stated to be vital to a regulatory filing. Meridian deli…
- Bharat Life Re buys a data-analytics licence from TechMine. The contract says the software will be supported by a helpdesk 24x7. The helpdes…
- Vikram Pensions Ltd hires Ishaan, a data vendor, to supply a mortality dataset by a fixed date. Ishaan knows only that the data is for 'inte…
- Meera, an actuary, agreed to provide a valuation report to Deccan Pension Trust. Before she started, the trustees asked the court to compel …