ACCA Applied Skills · Performance Management · Planning and operational variances

Tarn Co's original standard price for material was $8 per kg. The ex-post price was $9 per kg. Actual purchases were 5,000 kg at $8.70 per kg. What are the material planning price variance and operational price variance?

Planning price variance is (9 − 8) × 5,000 = $5,000 adverse, and operational price variance is (9 − 8.70) × 5,000 = $1,500 favourable. Together they give the traditional $3,500 adverse price variance.

  1. APlanning $5,000 adverse; operational $1,500 favourableCorrect
  2. BPlanning $5,000 adverse; operational $1,500 adverse
  3. CPlanning $1,500 favourable; operational $5,000 adverse
  4. DPlanning $3,500 adverse; operational $1,500 favourable

Explanation

Planning price = (9 − 8) × 5,000 = $5,000 adverse. Operational price = (9 − 8.70) × 5,000 = $1,500 favourable, since actual cost was below the revised standard. Total of $3,500 adverse equals the traditional price variance (8 − 8.70 = 0.70 × 5,000).