ACCA Applied Skills · Performance Management · Planning and operational variances
Tarn Co's original standard price for material was $8 per kg. The ex-post price was $9 per kg. Actual purchases were 5,000 kg at $8.70 per kg. What are the material planning price variance and operational price variance?
Planning price variance is (9 − 8) × 5,000 = $5,000 adverse, and operational price variance is (9 − 8.70) × 5,000 = $1,500 favourable. Together they give the traditional $3,500 adverse price variance.
- APlanning $5,000 adverse; operational $1,500 favourableCorrect
- BPlanning $5,000 adverse; operational $1,500 adverse
- CPlanning $1,500 favourable; operational $5,000 adverse
- DPlanning $3,500 adverse; operational $1,500 favourable
Explanation
Planning price = (9 − 8) × 5,000 = $5,000 adverse. Operational price = (9 − 8.70) × 5,000 = $1,500 favourable, since actual cost was below the revised standard. Total of $3,500 adverse equals the traditional price variance (8 − 8.70 = 0.70 × 5,000).
Did you get it right without looking?
One question tells you little. A timed set on Planning and operational variances shows your real accuracy, how long you take and where you lose marks.
More Planning and operational variances questions
- Which of the following labour variances would most appropriately be classified as a planning variance rather than an operational variance?
- Garner Ltd set a standard labour rate of $12.00 per hour. After the budget was agreed, the standard was revised to a realistic $13.50 per ho…
- Tolland Co's original flexed budget labour cost for the actual output was $90,000. The same output, costed at the revised (ex-post) standard…
- Bram Co budgeted to produce 1,000 units using 4 hours of labour per unit at a standard rate of $15 per hour. Because of a new national wage …
- Which of the following is a valid criticism of reporting only traditional (non-planning) variances when the original standard was set unreal…
- Which variance is classed as an operational variance when a revised (ex-post) material price is used as the benchmark?