ACCA Applied Skills · Performance Management · Planning and operational variances
Tarn Co originally budgeted a material price of $5 per litre. The revised ex-post price was $6 per litre. The purchasing manager bought 10,000 litres at $5.70 per litre. Which of the following best describes the performance of the purchasing manager?
The purchasing manager performed favourably. The operational price variance is $3,000 favourable, since $5.70 was paid against a realistic revised price of $6. The $10,000 adverse planning variance reflects an unrealistic original standard and is not the manager's responsibility.
- AFavourable, because the operational price variance is $3,000 favourableCorrect
- BAdverse, because the total price variance is $7,000 adverse
- CAdverse, because the planning variance is $10,000 adverse
- DFavourable, because the planning variance is $3,000 favourable
Explanation
Operational variance = (6.00 – 5.70) × 10,000 = $3,000 favourable. The planning variance of $10,000 adverse (1 × 10,000) is outside the manager's control, and the total of $7,000 adverse would unfairly penalise the manager. Performance should be judged on the operational variance.
Did you get it right without looking?
One question tells you little. A timed set on Planning and operational variances shows your real accuracy, how long you take and where you lose marks.
More Planning and operational variances questions
- Tolland Co's original flexed budget labour cost for the actual output was $90,000. The same output, costed at the revised (ex-post) standard…
- Bram Co budgeted to produce 1,000 units using 4 hours of labour per unit at a standard rate of $15 per hour. Because of a new national wage …
- Which of the following is a valid criticism of reporting only traditional (non-planning) variances when the original standard was set unreal…
- Which variance is classed as an operational variance when a revised (ex-post) material price is used as the benchmark?
- Brindle Co budgeted 3 labour hours per unit at an original standard rate of $10 per hour. The ex-post (revised) standard is 3.5 hours per un…
- A company set a standard material price of $10 per kg. Due to a market-wide shortage, the actual price paid was $12 per kg, and the ex-post …