Torrin Co uses absorption costing and a standard fixed overhead absorption rate of $8 per labour hour. Budgeted output was 5,000 units at 2 labour hours per unit. Actual fixed overheads incurred were $84,500. What is the fixed overhead expenditure variance?

The fixed overhead expenditure variance is $4,500 adverse. Budgeted fixed overhead is 5,000 units x 2 hours x $8, which equals $80,000, and actual spending was $84,500. Spending more than budget gives an adverse variance of $4,500.

  1. A$4,500 adverseCorrect
  2. B$4,500 favourable
  3. C$10,000 adverse
  4. D$5,500 adverse

Explanation

Budgeted fixed overhead = 5,000 x 2 x $8 = $80,000. Actual $84,500 exceeds budget by $4,500, so the expenditure variance is $4,500 adverse. Option $10,000 is wrong because it compares to a different base; the expenditure variance uses budget, not absorbed, cost.

Did you get it right without looking?

One question tells you little. A timed set on Variance calculations and analysis shows your real accuracy, how long you take and where you lose marks.

More Variance calculations and analysis questions