ACCA Applied Knowledge · Management Accounting · Variance calculations and analysis
Which of the following is the most likely cause of an adverse labour rate variance combined with a favourable labour efficiency variance?
Using more highly skilled, higher-paid workers is the most likely cause. They are paid above the standard rate, producing an adverse rate variance, but they work faster than standard and use fewer hours, producing a favourable efficiency variance.
- AUse of more highly skilled, higher-paid workers who work faster than standardCorrect
- BUse of untrained temporary staff paid below the standard rate
- CA machine breakdown causing idle time
- DPoor quality materials causing slower working
Explanation
Higher-paid skilled workers cost more per hour, giving an adverse rate variance, and they complete work in fewer hours, giving a favourable efficiency variance. Untrained staff paid less would produce the opposite pattern (favourable rate, adverse efficiency). Breakdowns and poor materials would produce adverse efficiency or idle time.
Did you get it right without looking?
One question tells you little. A timed set on Variance calculations and analysis shows your real accuracy, how long you take and where you lose marks.
More Variance calculations and analysis questions
- Standard labour is 3 hours per unit at $12.00 per hour. Dorset Co produced 1,200 units, using 3,750 hours at an actual rate of $12.40 per ho…
- A company's fixed overhead expenditure variance is $2,000 adverse and its volume variance is $5,000 favourable. What is the total fixed over…
- Fenwick Co uses a standard of 2 hours per unit at $9 per hour. Actual output was 2,500 units. Actual hours paid were 5,200, of which 200 wer…
- Zeta Ltd uses standard marginal costing. Budgeted sales were 2,000 units and actual sales were 2,150 units. The standard contribution is $12…
- Brindle Co has a standard labour rate of $9 per hour. In June, 3,200 hours were paid at an actual cost of $30,080, of which 150 hours were r…
- Kestrel Ltd budgeted fixed production overheads of $60,000 for the period, based on 12,000 units at 2 labour hours per unit. Actual fixed ov…