CS Professional · Arbitration, Mediation and Conciliation · Preparation and Execution of Arbitral Award
Under section 33, Mehra Infra requests an additional award on an omitted claim on day 20 after receiving the award, and the tribunal finds the request justified. Which statement is correct about the time available to the tribunal?
Where the tribunal finds the request justified, it must make the additional award within sixty days from receipt of the request. Section 33(6) permits the tribunal itself to extend that period if necessary, so no Court extension is required.
- AIt must make the additional award within sixty days from receipt of the request, though it may extend this period if necessaryCorrect
- BIt must make it within thirty days from the date of the original award, with no extension
- CIt must make it within sixty days from the date of the original award, with no extension
- DIt must make it within ninety days, and only the Court can extend the time
Explanation
Section 33(5) gives sixty days from receipt of the request. Section 33(6) lets the tribunal extend the period if necessary. The thirty-day period relates to the party's request or to correction, not to making the additional award.
Did you get it right without looking?
One question tells you little. A timed set on Preparation and Execution of Arbitral Award shows your real accuracy, how long you take and where you lose marks.
More Preparation and Execution of Arbitral Award questions
- A tribunal seated at Hyderabad by agreement between Desai Motors Ltd and Khan Auto Parts passes an award that carries no signature date and …
- Mehta Exports Ltd and Sundaram Traders agreed in their arbitration clause that the tribunal need not give reasons for its award. The sole ar…
- In a domestic arbitration, pleadings under section 23(4) were completed on 1 April 2025. The parties consented to extend the time for the aw…
- A three-member tribunal sitting in Pune decides a dispute between Kaveri Textiles Ltd and Sahyadri Dyes Pvt Ltd. Two arbitrators sign the aw…
- A tribunal awards Rs 40,00,000 to Veena Constructions against Omkar Infra. The award is silent on post-award interest and the parties have n…