CMA Intermediate · Cost Accounting · Standard Costing and Variance Analysis
Verma Industries budgeted sales of 5,000 units at Rs 80 per unit with a standard cost of Rs 60 per unit. Actual sales were 4,600 units. Under the margin method, what is the sales volume variance?
The margin-method sales volume variance is Rs 8,000 Adverse. Actual sales fell 400 units short of budget, and each unit carries a standard profit of Rs 20 (80 - 60), so the lost profit is 400 x 20 = Rs 8,000.
- ARs 8,000 AdverseCorrect
- BRs 32,000 Adverse
- CRs 24,000 Adverse
- DRs 8,000 Favourable
Explanation
Margin method volume variance = (Actual qty - Budgeted qty) x Standard profit per unit = (4,600 - 5,000) x (80 - 60) = 400 x 20 = Rs 8,000 Adverse. Option B uses the selling price of Rs 80 (turnover method), giving 32,000, which is the wrong base for the margin method.
Did you get it right without looking?
One question tells you little. A timed set on Standard Costing and Variance Analysis shows your real accuracy, how long you take and where you lose marks.
More Standard Costing and Variance Analysis questions
- Rohini Plastics budgets fixed overheads of ₹2,00,000 for 10,000 units. Actual output is 8,000 units and actual fixed overheads are ₹2,10,000…
- Kapoor Textiles sets a standard of 5 labour hours per unit at ₹40 per hour. The standard time includes 10% of the paid time as normal idle t…
- Standard for one unit of a product is 5 kg of material at Rs 20 per kg. In a period 1,000 units were produced, using 5,300 kg of material bo…
- Standard for one unit of a product at Surat Textiles: 5 hours at ₹40 per hour. In a month, 800 units were produced, with 4,200 hours worked …
- Under the turnover (value) method of sales variance analysis, the sales value variance is the difference between:
- Standard labour cost for output of a product at Indore Tools: 600 hours at ₹30 = ₹18,000. Actual: 640 hours paid at ₹29 = ₹18,560, of which …