Which of the following is a cost reduction technique rather than a cost control technique?
Value engineering is a cost reduction technique because it redesigns a product or its process to lower unit cost while keeping required function. The other options compare with or enforce existing budgets and standards, which is cost control rather than permanent reduction.
- AValue engineering of a product before launchCorrect
- BMonthly comparison of actual and budgeted overhead
- CSetting a standard cost for labour hours
- DIssuing materials only against authorised requisitions
Explanation
Value engineering redesigns the product to lower its cost while retaining function, giving a permanent reduction in unit cost. The other options monitor or restrict spending against existing targets, which is cost control.
Did you get it right without looking?
One question tells you little. A timed set on Cost reductions and value enhancement shows your real accuracy, how long you take and where you lose marks.
More Cost reductions and value enhancement questions
- A company's standard material cost per unit is $40. Actual material cost has been $42 per unit because of price rises, and management respon…
- Which of the following is a typical technique used to close the cost gap under target costing?
- Which statement about value engineering is correct?
- A value analysis team examines a product component with these assessed elements: cost value of $12, exchange value of $15, esteem value of $…
- A council spent $240,000 on a training programme and delivered 1,600 training hours against a plan of 2,000 hours at a budget of $250,000. W…
- A company is value engineering a product with a target selling price of $80 and a required margin of 25% on selling price. The current estim…