Which of the following is the most appropriate treatment of the cost of a job that is completed and found to have spoilage due to abnormal reasons (i.e., not inherent in the job's normal operations) in job costing?

Abnormal spoilage cost is charged to the Costing Profit and Loss Account, because it arises from avoidable causes and is not a normal cost of the job. Loading it on the job or on overheads would overstate job costs and distort quotations.

  1. ACharge it to the Costing Profit and Loss AccountCorrect
  2. BCharge it to the specific job as part of its normal cost
  3. CSpread it over all jobs in progress through the overhead rate
  4. DCredit it to the Work-in-Progress Control Account

Explanation

Abnormal spoilage is not a normal cost of the job and is not expected in routine operations. Its cost is therefore written off to the Costing Profit and Loss Account. Adding it to the job or to overheads would inflate costs and distort pricing; crediting WIP does not remove the loss.