CA Intermediate · Cost and Management Accounting · Job Costing
Which of the following is the most appropriate treatment of the cost of a job that is completed and found to have spoilage due to abnormal reasons (i.e., not inherent in the job's normal operations) in job costing?
Abnormal spoilage cost is charged to the Costing Profit and Loss Account, because it arises from avoidable causes and is not a normal cost of the job. Loading it on the job or on overheads would overstate job costs and distort quotations.
- ACharge it to the Costing Profit and Loss AccountCorrect
- BCharge it to the specific job as part of its normal cost
- CSpread it over all jobs in progress through the overhead rate
- DCredit it to the Work-in-Progress Control Account
Explanation
Abnormal spoilage is not a normal cost of the job and is not expected in routine operations. Its cost is therefore written off to the Costing Profit and Loss Account. Adding it to the job or to overheads would inflate costs and distort pricing; crediting WIP does not remove the loss.
Did you get it right without looking?
One question tells you little. A timed set on Job Costing shows your real accuracy, how long you take and where you lose marks.
More Job Costing questions
- Mehta Tools charges a job with a cost of Rs 80,000 and finds that 5% of the units made are defective due to the specific requirements of tha…
- Which of the following best describes the treatment of a job cost sheet in job costing?
- Which of the following best describes a job cost sheet in a job costing system?
- Gupta Tools completed Job T-3 with direct material Rs 20,000 and direct labour Rs 15,000. Spoilage that is normal and inherent in the job's …
- In job costing, which document is used to accumulate the material, labour and overhead costs of a particular job, and from which the total c…
- In job costing, which document is used to collect and record the cost of direct materials, direct labour and overheads for each individual j…