CMA Final · Strategic Cost Management · Just in Time (JIT)
Which of the following is the primary reason a firm adopting Just in Time (JIT) purchasing typically negotiates long-term contracts with a small number of suppliers?
JIT firms use few suppliers on long-term contracts so that they receive frequent, small deliveries of reliably good quality straight to the production line. This removes the need for incoming inspection and large stocks, which is the core aim of JIT purchasing, unlike bulk buying or buffer stocks.
- ATo obtain larger quantity discounts by ordering in bulk batches
- BTo secure frequent, small-lot deliveries of consistent quality directly to the production lineCorrect
- CTo build up safety stock buffers against demand fluctuations
- DTo reduce the number of production cells on the shop floor
Explanation
JIT purchasing relies on a few reliable suppliers who deliver small lots frequently, with assured quality, so that inspection and stock-holding are minimised. Bulk ordering and buffer stock contradict the JIT philosophy of minimal inventory.
Did you get it right without looking?
One question tells you little. A timed set on Just in Time (JIT) shows your real accuracy, how long you take and where you lose marks.
More Just in Time (JIT) questions
- Which one of the following is a defining feature of a JIT purchasing arrangement between a manufacturer and its suppliers?
- Under JIT, a cell at Narmada Engineering has a set-up time of 2 hours per batch and runs 10 batches a month. Machine cost is Rs 600 per hour…
- Which of the following is a characteristic of a Just in Time (JIT) purchasing arrangement with suppliers?
- A manufacturer moving to Just in Time wants to compare its purchasing approach before and after. Which of the following is a characteristic …
- Kaveri Auto Components moves to JIT and cuts average inventory from Rs 24,00,000 to Rs 6,00,000. Its carrying cost is 15% per annum on avera…
- Himalaya Gears adopts JIT. Annual demand is 12,000 units. Before JIT, setup cost was Rs 1,800 per setup and carrying cost Rs 10 per unit per…