CMA Final · Strategic Cost Management · Just in Time (JIT)
Under backflush costing as used with JIT, which statement is correct?
In backflush costing, entries are made at the end, when output is completed or sold, and costs are worked backward to inventory and cost of goods sold. This avoids detailed work-in-process tracking, which suits JIT environments with very low inventories and short production cycles.
- ADetailed work-in-process accounts are maintained for each stage
- BCosts are recorded at the end of the process, working back from output to allocate costs to inventory and cost of goods soldCorrect
- CRaw material purchases are always charged directly to cost of goods sold
- DDirect labour is tracked job by job
Explanation
Backflush costing delays entries until finished goods or sales occur, then works backward to assign costs. It removes detailed WIP tracking. Charging all purchases to cost of sales is only a feature of some trigger points and not always.
Did you get it right without looking?
One question tells you little. A timed set on Just in Time (JIT) shows your real accuracy, how long you take and where you lose marks.
More Just in Time (JIT) questions
- Under JIT, a cell at Narmada Engineering has a set-up time of 2 hours per batch and runs 10 batches a month. Machine cost is Rs 600 per hour…
- Which of the following is the primary reason a firm adopting Just in Time (JIT) purchasing typically negotiates long-term contracts with a s…
- In a JIT system with backflush accounting, which of the following correctly describes when costs are typically charged to cost of goods sold…
- A manufacturer moving to Just in Time wants to compare its purchasing approach before and after. Which of the following is a characteristic …
- Which of the following is a characteristic of a Just in Time (JIT) purchasing arrangement with suppliers?
- Rao Engineering adopts JIT and plans to cut average inventory from Rs 24,00,000 to Rs 6,00,000, a release of Rs 18,00,000. Cost of capital i…